Bullhead City, AZ
Home MenuNeighborhood Street Improvement Program 29 (NSIP29)
Fiscal Year 2017-2018
Introduction
NSIP 29 outlines a list of roads that comprise 20% of the City’s total road infrastructure to be treated this fiscal year, July 2017-June 2018, with either a slurry seal or microsurface treatment. The City plans to operate the slurry machine, resurfacing a few streets every week, for as long as the weather and other conditions permit. The city asks all residents that will be affected by the maintenance to check this page frequently for updates on the progress of NSIP 29.
Read the NSIP 29 METHODOLOGY page for a list of all of the streets slated to receive treatment.
Read our Slurry Frequently Asked Questions for answers to commonly asked questions about the slurry seal treatment.
If you have unanswered questions about NSIP 29, send an email to slurry@bullheadcity.com.
If you need to discuss an urgent matter related to NSIP 29, call (928)234-8752.
UPDATES/PROGRESS
The posted schedules for NSIP 29 are rough estimates only. There are a number of variables including weather conditions and equipment failure that can cause unexpected delays or changes in the schedule. The most up to date information will always be posted in this section of this page.
UPDATE 4/19: Maintenance on McCormick from the highway to 800 Ft East will be rescheduled.
UPDATE 3/20: Due to equipment failure, maintenance scheduled for March 20th has been rescheduled.
UPDATE 03/12: Due to equipment failure, maintenance scheduled for March 15th has been rescheduled.
UPDATE 03/12: Due to equipment failure, maintenance scheduled for March 14th has been rescheduled.
UPDATE 03/12: Maintenance scheduled for March 13th has been rescheduled.
UPDATE 03/12: Maintenance scheduled for March 12th on Rising Sun Rd and King Rd has been rescheduled.
UPDATE 02/27: All maintenance for this week has been cancelled.
UPDATE 02/26: Kalill and Childers way have been rescheduled to a later date.
This Week's Scheduled Maintenance
The City of Bullhead City Public Works Department will begin slurry seal/micro surface treatment on the following streets as a part of the 29th Neighborhood Street Improvement Program (NSIP 29):
Monday April 16th
- Sundrops Dr from Indian Head Dr to Sharon Rd
- Sundrops Ct from Sharon Rd to the end of Pavement
- Sundance Dr from Indian Head Dr to Sharon Rd
- Sundance Dr from Sharon Rd to Florence Ave
Tuesday April 17th
- East bound lanes of McCormick Blvd from Pegasus Ranch Rd to Indian Head Dr
- Sun Lane Dr from the end of pavement to the end of pavement
Wednesday April 18th
- Westbound lanes of McCormick Blvd from Indian Head Dr to Pegasus Ranch Rd
- McCormick Blvd from Pegasus Ranch Rd through Park Crest Dr
Thursday April 19th
- McCormick Blvd from Highway 95 to 800 feet east to curb and gutter - Cancelled
- Landon Drive East from Sun River Rd to Sunflower Dr
- Sun Flower Dr from Landon Dr East to Campbell Rd
The scheduled days are a target, and a number of factors can put city crews either ahead or behind schedule. Anyone who will be affected by this maintenance is highly encouraged to check the City’s website frequently at www.bullheadcity.com/nsip29 for the most up to date information. Anyone with concerns, comments, or questions about NSIP 29 should send an email to slurry@bullheadcity.com. Anyone with an urgent matter relating to NSIP 29 should call (928)234-8752.
Next Week's Scheduled Maintenance
SUBJECT TO CHANGE: Preliminary schedules for the upcoming week of Maintenance are typically formed the Wednesday before work is to begin. A more firm schedule is released the Friday before work is scheduled to begin. All schedules are targets that may or may not be met depending on factors such as weather and equipment failure.
Map of NSIP 29
Read the full list of streets slated to be a part of NSIP 29 on METHODOLOGY page.